October 1 Workday

Bruce touches up the paint before we lay the decking

Bruce @6’ discusses work priorities with Dee @6’ & Matt @6’

on a super smokey day with the AQI @~175

Cement prep was on our minds today. A pumper truck is planned for the next work day. Different types of prep work needed to be completed to prepare for:

  • A large pad for the Gritty Gravel Barn

  • The overlook hillside support structure

  • Portals on both sides of the Redwood Canyon Tunnel

Some folks chose to work inside the shop to shelter from the thick smokey air.


Photos - click on images for text descriptions and large images