November 7 Workday

Bruce touches up the paint before we lay the decking

Mike and Randy secure decking to the Lumber Camp Bridge

A new phase in the progress for the Lumber Camp Bridge was reached this week. The decking was laid on the installed sections. Bruce supplied the lifting power to move supplies needed for the Lumber Camp Bridge from the workshop. Randy, Mike, & Ken then started to attach the PT decking material.

Bill and Kevin graded the Lumber Camp Loop using Bill’s cute tractor.

Kevin, Dee, Sierra, and Bob continued to add track panels and have now reached just below the riding arena.


Photos - click on images for text descriptions and large images