May 2020 Run Weekend

IMG_6114.jpeg

Our run weekend turned into a very successful work weekend. We had a hearty crew who were happy to be away from home and at the railroad. There were six projects we focused on:

  • Extending the grade beams for some of the trestle bents (see video below)

  • Welding the truss section in place

  • Installing hand railings

  • Switch maintenance

  • Curving and drilling rail for track panels

  • Locating the final home for the Redwood Canyon Bridge


Photos - click on images for text descriptions and large images


Videos

It took a large team to extend the grade beam for the Lumber Camp Bridge’s trestle. Miles liked the electric hammer; he was disappointed that I did not follow-up on my proposal to bring dynamite to bear on the task.