July 06 Workday

Carl returned and helped Bob install a new blade. 4 hands are better than 2 to tame the blade

Mike had the biggest crew of the day installing the Caboose Camp to Redwood Tunnel foot bridge foundation. It was a very successful day!  Got all 8 posts in the ground an average of 4 feet deep - until resistance was met. Many Thanks to Matt, Dee, Dean, Randy, Kevin W, and Bill.

The mainline is out by the riding arena for drain pipe repairs. We expect the mainline to be out through the July run. During the July run we will be limited to the old Rabbit Flat loop. The serpentine section below the riding arena may also be open (TBD).

We are organizing an all hands workday on Saturday the 22nd as a portion of the right of way will be closed.


Photos - click on images for text descriptions and large images