April 15 Workday

Bruce touches up the paint before we lay the decking

Bill & Kevin rejoice after setting a gutter board

Bill and Bruce led a multi day work week to set gutter boards along the caboose route. Completing the gutter boards is required in order to continue laying base rock. Once the base rock is laid and tamped track laying can commence.